Some supplier relationships require you as the purchasing organization to provide the supplier with the components used in their part of the value creation. A typical example in manufacturing would be assembly. Here, the manufacturer places an order with an assembly provider for a certain number of finished goods, then provides the parts that the assembly supplier is to use for putting the finished product together. These components are usually associated with a BOM, as evidenced by the figure below.
Standard Subcontracting Approach
In SAP, there are multiple ways of setting up this transaction, but many approaches add more complexity than they are worth. For example, you can choose to create plants that are technically the supplier’s locations and track your inventory as you move it to these locations for finishing. For each transaction requiring subcontracting, you then have to issue a PO and create multiple goods movements and accounting entries internally to support the process. This approach requires more manual effort and accounting acrobatics than is optimal. The most straightforward way to support subcontracting processes is to use the standard subcontracting approach in the system. The process is as follows:
  1. Select PO type L when creating the purchase order for a subcontracted item. L is the subcontracting PO type and allows you to create subitems manually or via a BOM explosion automatically for the components to be provided to the subcontractor. Although the final product doesn’t necessarily require a materials master, the components do require a material master record for this process in SAP.
  2. For the MRP to pick up the subcontracting order correctly, you must maintain a subcontracting entry for the associated material in its MRP area assignment, an MRP-relevant source of supply/quota agreement with the subcontracting setting (source lists are not supported in SAP S/4HANA before version 1709 for MRP, so you would need to use a quota agreement as a workaround in these versions), and a BOM containing the components. During the MRP run, the system explodes the BOM requirements and classifies dependent, subcontracting elements as such.
To flag a material master directly for subcontracting, choose a half finished (HALB) or finished (FERT) material, and in the MRP tab maintain the Special Procurement field with option 30 for the plant, as shown in the figure below.
Subcontracting in SAP S/4HANA
In previous versions of SAP ERP, component materials to be provided to the subcontractor could be planned as a separate stock. However, with SAP S/4HANA, a subcontracting MRP area is the default option for subcontracting planning. Subcontracting will appear under the general plant stock if there is no MRP area maintained for the supplier.
Also, in previous versions of SAP ERP, you could check subcontracting stocks by supplier by running reports from a specific IMG menu path. This transaction is now available as an app in SAP S/4HANA, as shown in the next figure.
In SAP S/4HANA, MRP areas have to be created for every subcontractor; if MRP area–specific material master records don’t exist, MRP uses default planning parameters. This differs from classic SAP ERP for subcontracting, in which you could plan either with or without MRP areas. If you elected to plan without MRP areas, you weren’t able to use the full functionality around lot sizing and were only able to order full lot sizes. If you chose the MRP area route, material data on an MRP area was required for all components. These two options are now combined into one driven by MRP areas, but it doesn’t require material data on all components and can support full-lot sizing and sourcing functionality.
Upgrading MRP Subcontracting to SAP S/4HANA
To upgrade MRP subcontracting processes in SAP ERP to SAP S/4HANA, you need to take stock of your existing subcontracting suppliers and processes and identify any gaps, execute a standard upgrade to SAP S/4HANA, and then at postprocessing proceed as follows:
  1. Maintain subcontracting MRP areas for all subcontracting suppliers requiring provision stocks to be planned separately from requirements. The customizing entry in the supplier master is sufficient to trigger stock transfers and reservations from the plant to the subcontracting MRP area. You only have to maintain entries in the material masters if special situations exist for lot sizing, purchase requisitions/orders, and/or third-party order processing.
  2. Run regenerative MRP and test.
Subcontracting Order Collaboration
As detailed in this blog post, the standard subcontracting process in SAP entails a leap of faith to a degree, which some MRP controllers and their ilk are unwilling to make. Upon issuing a subcontracting PO and shipping out the components to the supplier, the buyer doesn’t technically receive updates on the production of the order until the final product or subassembly with the components is shipped back from the supplier to the buyer. Tracking the materials and valuations, which technically still belong to the buying organization, becomes difficult using the standard process. This often is used as justification by finance and other stakeholders on the buyer side for setting up phantom plants to represent the supplier and then moving and tracking the materials in these plants. This creates a host of additional transactions for each subcontracting order and does scale well.
SAP Ariba Supply Chain Collaboration for Buyers provides an extra layer of visibility that has been sought in the subcontracting process, including component receipt and consumption notices from the supplier, as well as full B2B-level manufacturing visibility into the supplier’s progress.
The next figure shows how in using the supplier portal on the Ariba Network, a supplier can log in and confirm the consumption of subcontracting components into the assembly.


Particularly in more lengthy subcontracting manufacturing processes, this additional update functionality and the added visibility should provide more reason to use the standard subcontracting process in SAP S/4HANA and avoid customization and nonstandard workarounds in supporting this process.
Excerpt from the book Sourcing and Procurement in SAP S/4HANA by Justin Ashlock. Used with permission of SAP PRESS. All rights reserved.
----------------------------------------------------------------------------------------------------------
Sign up for SAP PRESS newsletters to get even more SAP tips and tricks delivered to you monthly!
Follow SAP PRESS on LinkedIn for info on new releases, news, and more!

Source: https://www.linkedin.com/pulse/subcontracting-within-sourcing-procurement-sap-s4hana-sean-fesko/

Um comentário:

  1. We have to thank and share such a nice blog post and interesting information. It is helpful for develop my knowledge, people always searching for this type of posts.
    Procurement Management Software
    Procurement Management Software India
    Procurement Management Software
    e Procurement Management Software

    ResponderExcluir