segunda-feira, 24 de fevereiro de 2020

Basics of MRP Area

The purpose of this document is to explain the basics of MRP area, steps involved in activating MRP area and to use it in different possible ways.
As we know MRP runs at plant level (centralized), but as per business need we may have to plan MRP for individual & independent planning areas (decentralized). This can be achieved by activating MRP areas. These MRP areas are fully configurable organizational units within ECC where MRP can be run individually. So we can broadly classify running MRP in 2 major ways.
MRP1.PNG
  • MRP at plant level: The system adds together stocks from all of the individual storage locations to determine total plant stock. The requirements are combined in the planning run and procurement elements are created for these pegged requirements with unknown sources. Individual storage locations can be planned separately or be excluded from planning.
Illustration:
MRP1_1.PNG
  • MRP area level: Only the stocks from the storage locations or subcontractor assigned to the respective MRP area are taken into account. The requirements in this particular MRP area are combined and procurement elements are created for them. This enables us to plan material requirements specifically for certain areas (MRP areas).

Illustration:
MRP_Area.png
You can define MRP areas within a plant and carry out MRP specifically for that particular area, for example in above illustration, for MRP area M0001 can be planned independently without running MRP for plant FP01.
In each MRP area you can control staging and procurement of parts that are produced in house or externally. All MRP procedures are supported by MRP areas and one can display the result of MRP run for each MRP area.

MRP Area (definition):

As per SAP, MRP Area represents an organizational unit for which material requirements planning is carried out independently”

MRP Area is functionality for special planning process that enables you to carry out planning not only at plant level but also at different planning levels (eg, storage location & sub-contractors). There are 3 types of MRP areas in SAP
  • Plant MRP Area
  • MRP Areas for storage location
  • MRP Areas for Subcontractors

Plant MRP area:

MRP area can be created at plant level. On doing so, system combines all its storage locations and stock with subcontractors under that MRP area. When you define MRP areas for storage locations and for subcontractors and assign material to newly created MRP areas with in plant then the plant MRP area gets reduced by exactly the numbers of subcontractors and storage locations. This is because they will now be planned separately in new MRP areas.

MRP area for storage location:


MRP area can also be defined for storage location or multiple storage locations. Material requirements for this storage location are then planned separately from the rest of the plant. Important point to note here is that you can assign 1 storage location to only 1 MRP area but you can have multiple storage locations under single MRP area. It’s a N to 1 relationship.

MRP Areas for Subcontractors:


You can also define an MRP area for each subcontractor. Important point to note here is that a subcontractor can be assigned to only one MRP area in a plant. An MRP area of the subcontractor type can only contain one subcontractor. It’s a 1 to 1 relationship.

How to setup MRP area in SAP

There are 2 aspects of setting up MRP area. First one is to activate it in customizing and second part it to set up master data (i.e. adding materials to that particular MRP area in material master).
MRP with MRP area is not operational until you assign MRP area to a particular material in material master or in order words create a MRP area segment. If you have not assigned a material to an MRP area, that is, you have not created an MRP area segment in the material master, the material will continue to be planned in the plant MRP area only.

Step 1 – Converting Planning file entries

Path: SPRO > Production > Material Requirement Planning > Master Data > MRP Areas > Convert Planning file entries for MRP areas – OM0F or SE38 program RMDBVM00

1.PNG
When we convert planning file entries for MRP area, system creates plant MRP area for each plant. Following entries from below tables are converted. Planning file entries are maintained in MRP file which are converted to MRP area file in below tables.
Planning file entries in MDVM are converted to DBVM
Planning file entries in MDVL are converted to DBVL
Planning file entries in KDVM are converted to KBVM
Planning file entries in KDVL are converted to KBVL
2.PNG
If you are running converting planning files for the first time then system will automatically create plant MRP areas. These new entries can be seen in OMIZ under plant MRP area with area type “01”.
IMP note: After the conversion, contents of MDVM/MDVL/ KDVM/KDVL are deleted and entries are created in DBVM/ DBVL/ KBVM/ KBVL.
Step 2 – Define MRP area in SPRO – OMIZ

Path: SPRO > Production > Material Requirement Planning > Master Data > MRP Areas > Define MRP areas

3.PNG

MRP area has 3 types (01, 02 & 03) and system will allow you to have MRP areas in below types only (Plant, Storage location or Sub Contractor)

4.PNG

Plant MRP area should have same name as plant so you can have only one entry for plant MRP area. For example plant 1000 will have plant MRP area as 1000.
In order to maintain consistency and uniformity, only MRP areas of the type ‘plant’ are allowed to have 1-4 digits key. Sloc MRP area should have minimum of 5 digits. Example M0001 etc…
You can only have 1 sub-contractor vendor assigned to 1 MRP area. Multiple vendors cannot be grouped together in a single MRP area.
You can have multiple storage locations combined together in a single MRP area.
You can only one entry for plant in plant MRP area. Multiple plants cannot be grouped together in a single MRP area.
Once MRP area is defined, next step is to Activate MTP area

Step 3 – Activating MRP Areas – OM01

Path: SPRO > Production > Material Requirement Planning > Master Data > MRP Areas > Activate MRP for MRP areas

NOTE: MRP areas are activated at client level. Once you activate it, it will be available for all plants and MRP areas features would be available to use.

5.PNG
This sums up setting up MRP area configuration in SAP customizing.
You can find following changes due to activation of MRP area. These are just few for example
MD61 – PlR creation
6.PNG
MRP
7.PNG
Material Master
8.PNG
Stock Requirement list
9.PNG

Step 4: Master data for MRP area

The material will not be considered in MRP area planning until it’s extended to MRP area.  Following steps shows how to extend a material in MRP area. You can extend a material to multiple MRP areas based on the need.
Go to change material master under MRP 1 screen and assign MRP area as shown below:
10.PNG
You will have additional views for MRP 1, MRP 2, Forecast & Consumption values. You need to fill required fields as per your need.
12.PNG
When you assign a material to a new MRP area, a new record for this assignment gets added in the planning file. You have an option to define individual MRP and forecast parameters for each MRP area that you assign to a material. These parameters can differ from those defined in the material master at plant level. As an example, you can have different MRP controllers, lot size or MRP type for each individual MRP areas that is assigned to a material.
Users can set up different forecast model and consumption values in MAR area tabs. Once MRP with MRP area is activated, ATP check is also activated at MRP area level.

Scope of planning with MRP area

You can create scope of planning run if you want to carry out total planning for limited MRP areas. In case you do not give any MRP area in total planning run, system will consider all MRP areas under a plant and plan for them in total planning.
13.PNG
For single item planning system, in MD02 & MD03 system plans a material only in the specified MRP area.
Sample Scenario:
Let’s consider a material Assembly maintained in plant ZSY1 under 2 storage locations (ZSY3 & ZSY4)
Sloc ZSY3 maintained in MRP area MA001. Assembly is extended to MA001 with following stock situation
ZSY3 – 100 (under storage location MRP area MA001)
ZSY4 – 150 (under Plant MRP area ZSY1)
Lot size for same material is maintained as FX (fixed lot size) in MA001 MRP area and EX in plant MRP area ZSY1
14.PNG
Total stock MMBE
15.PNG
MD04 – MRP Area ZSY1
16.PNG
MD04 – MRP Area MA001
17.PNG
Let’s have requirement from a Sales order for plant ZSY1, it will come under plant MRP area ZSY1
For testing, we can also have PIR created for specific MRP area MA001
Here is the stock situation of MD04 with sales order in Plant MRP area
18.PNG
Stock requirement for MRP area MA001:
20.PNG
If we run MD02 for plant ZSY1, system will only consider plant MRP area and will not plan for MRP area MA001 as it’s a separate planning area
21.PNG
MRP area MA001 is untouched:
22.PNG
After running MRP for MA001 system creates planned order for 200 quantities
23.PNG
Material Assembly was maintained as EX lot size in plant MRP area and with fixed lot size 200 in MA001 hence planned order of 200 Qty created in MA001. In this way separate planning parameters can be maintained to run requirement planning using MRP areas.
~~~~~~~~~~~~~~~
Thank you for reading this document. Please feel free to suggest any change and modification needed to improve the document.
*Scenarios related to MRP areas will be covered in a separate document. The link will be added below once completed

Um comentário:

  1. Do you understand there is a 12 word phrase you can say to your partner... that will induce deep feelings of love and instinctual appeal for you buried inside his chest?

    Because deep inside these 12 words is a "secret signal" that fuels a man's impulse to love, treasure and care for you with his entire heart...

    12 Words That Trigger A Man's Desire Response

    This impulse is so built-in to a man's brain that it will drive him to try harder than before to take care of you.

    As a matter of fact, fueling this dominant impulse is absolutely binding to achieving the best possible relationship with your man that as soon as you send your man a "Secret Signal"...

    ...You will immediately find him expose his soul and mind to you in a way he haven't expressed before and he will distinguish you as the only woman in the universe who has ever truly appealed to him.

    ResponderExcluir